One by One - June 2018 Update

Updated: Nov 28, 2019

Here are a few shots of our newest completions. 1 more should be done by the end of the month (July 2018). It's a slow process but we keep plugging along. There are now 4 remodeled rooms plus the almost completed one. 2 are kings, the other 3 have 2 beds. It's all about balance, right?





More good news...

We only have a few rooms that still need new beds. I hear rumor those will be arriving early next month.


The updated internet is slated for mid July. Keeping fingers crossed as there has been more than 1 or 2 delays. TV and telephone should follow shortly thereafter. All the rooms now have the 55" screens BUT until the updates are finished, we still have to reset them sometimes. If it happens to you (locked on a channel) just let us know - it takes about 5 minutes to get it fixed up.